The Little Creek Project involved the construction of a new diversion structure and re-graded the existing stream channel.
The new diversion structure included a new fish ladder with screens, adjustable head gates, measuring device, and a water gap modification.

Three diversions were part of this project and employed similar methodology in construction. In all SLC imported 8,000 CY of select fill and/or stream simulation rock, and nearly 4,000 CY of large boulders for rock weirs and fish rock clusters.